Two months working as often as we could (we did have 4 days off over Christmas!) and we've now completed virtually all of the First Fix joinery.
All the internal partitions are in place, some are now gyproc'd on one side, and we're now focussing on fitting the heat recovery system ducting to all the rooms.
We will be looking to commence electrical first fix in February with plumbing following close after that. It's beginning to look and feel like a house!
Some more pics. Needless to say we're fairly exhausted with it all, but heyho - it literally won't build its self!
 |
View from the front door lobby |
 |
Master bathroom |
 |
Courtyard |
 |
Master bedroom looking up at en-suite, walk in wardrobe and dressing area |
 |
Utility room with connecting corridor |
 |
Bedroom 2 |
 |
Guest Bedroom - the Kennedy/Mannion/Cima/Ketley/McNair Suite |
 |
Two bedrooms to left, master bath ro right, utility at the bottom of the corridor |
 |
One day there will be stairs here! |
0 Comments:
Post a Comment
Note: only a member of this blog may post a comment.
Subscribe to Post Comments [Atom]
<< Home