Internal studwork complete!

Two months working as often as we could (we did have 4 days off over Christmas!) and we've now completed virtually all of the First Fix joinery.

All the internal partitions are in place, some are now gyproc'd on one side, and we're now focussing on fitting the heat recovery system ducting to all the rooms.

We will be looking to commence electrical first fix in February with plumbing following close after that. It's beginning to look and feel like a house!

Some more pics. Needless to say we're fairly exhausted with it all, but heyho - it literally won't build its self!
View from the front door lobby

Master bathroom

Courtyard

Master bedroom looking up at en-suite, walk in wardrobe and dressing area

Utility room with connecting corridor

Bedroom 2

Guest Bedroom - the Kennedy/Mannion/Cima/Ketley/McNair Suite

Two bedrooms to left, master bath ro right, utility at the bottom of the corridor

One day there will be stairs here!